The first cathode from Los Azules
At Argentina Cobre, in San Juan, the first copper cathode from Los Azules is shown. The project had received its environmental declaration in December 2024.

The second Argentina Cobre conference, organized by the magazine, brings together more than 1,200 attendees on August 4 and 5, 2025. In the photo, Governor Marcelo Orrego holds the piece, a square sheet in a transparent stand, beside Michael Meding, head of the project and chair of the conference.
The cathode reflects a design change. The 2017 assessment envisaged exporting concentrate; the June 2023 assessment proposes heap leaching the ore and producing finished copper for Argentina and for markets abroad. The company estimates that this reduces the use of fresh water and electricity by about 75%.
The deposit, in Calingasta, is not in production. A 2016 review places its discovery and its first studies between 2003 and 2011. In October 2025, the magazine presents it as the first copper project approved under the RIGI. In March 2026, Rob McEwen, president of the company, says that he expects to begin construction in 2027 and to produce in 2030.