CopperAugust 18, 1997 · Catamarca, Tucumán
Alumbrera starts milling
On August 18, 1997, the Bajo de la Alumbrera plant mills its first ore. Behind it are a 203-kilometer power line, a slurry pipeline and a port of its own. Large-scale copper and gold mining begins in the country.

Shashi Bubna, director of the project, reconstructs the work in an interview. The decision to proceed is announced on May 19, 1995, and construction begins in January 1996. There are five simultaneous projects, in Catamarca, Tucumán and Santa Fe, over more than one thousand kilometers: mine, slurry pipeline, high-voltage line, filter plant and port.
The equipment arrives from 24 countries. Moving more than 240,000 tonnes requires building 30 kilometers of temporary roads and reinforcing or bypassing twenty bridges. More than 2,500 operators and supervisors pass through training centers. The line is energized in January 1997, and the primary crusher receives the first rock on July 12.
The first shipment of concentrate leaves Puerto Alumbrera on October 29 of that year, and commercial production begins in February 1998. In June, the magazine reports that milling reaches 80,000 tonnes per day, the planned level, and that Karen Field succeeds Peter Freund as president.