CopperAugust 18, 1997 · Catamarca, Tucumán

Alumbrera starts milling

On August 18, 1997, the Bajo de la Alumbrera plant mills its first ore. Behind it are a 203-kilometer power line, a slurry pipeline and a port of its own. Large-scale copper and gold mining begins in the country.

Blue industrial building lit at dusk, with conveyor belts and hills in the background
Night view of the Bajo de la Alumbrera facilities, Catamarca, in August 1997. Photo: Issue 215, August 1997.

Shashi Bubna, director of the project, reconstructs the work in an interview. The decision to proceed is announced on May 19, 1995, and construction begins in January 1996. There are five simultaneous projects, in Catamarca, Tucumán and Santa Fe, over more than one thousand kilometers: mine, slurry pipeline, high-voltage line, filter plant and port.

The equipment arrives from 24 countries. Moving more than 240,000 tonnes requires building 30 kilometers of temporary roads and reinforcing or bypassing twenty bridges. More than 2,500 operators and supervisors pass through training centers. The line is energized in January 1997, and the primary crusher receives the first rock on July 12.

The first shipment of concentrate leaves Puerto Alumbrera on October 29 of that year, and commercial production begins in February 1998. In June, the magazine reports that milling reaches 80,000 tonnes per day, the planned level, and that Karen Field succeeds Peter Freund as president.

Electric shovel and two haul trucks at the bottom of an open pit of light-colored rock
Shovel and trucks in the Bajo de la Alumbrera open pit, in the interview with Shashi Bubna. Photo: Issue 215, August 1997.

All the moments

  • Gold
  • Silver
  • Copper
  • Lithium
  • Iron
  • Potash
  • Other minerals
  • Laws, institutions and the magazine