GoldJuly 25, 2014 · Santa Cruz
A 110-kilogram doré bar at Cerro Negro
On July 25, 2014, during the testing of the plant, Goldcorp obtains the first doré bar from Cerro Negro: 110 kilograms, most of it silver. Santa Cruz adds another large underground mine.

The bar comes after ten days of operation of the newly completed circuit. It is 7% gold and 93% silver. The plant has 165 workers. The deposit, 70 kilometers from Perito Moreno, then employs 1,400 people directly and 2,000 through contractors. The magazine records more than US$1.7 billion invested since 2010.
That year, Goldcorp buys Andean Resources, owner of Cerro Negro, for US$3.5 billion. On April 1, 2013, it begins to extract underground ore from the Eureka mine and stockpiles it on the surface while the plant is built. Work on the power line starts six months late and production may move to 2014, the company warns.
The company declares commercial production on January 1, 2015. In 2022, now in the hands of Newmont, the mine adds loaders operated from the surface. In May 2023, the company announces more than US$540 million to extend the mine life to 2034.