Other mineralsJuly 1989 · Jujuy
Journey to the center of El Aguilar
The magazine devotes a full dossier to Mina Aguilar, the Argentine leader in lead and zinc. The company signs an agreement to study a 50% expansion. The founder had worked there in the 1950s.

The company is incorporated in 1929 and ships concentrates from 1936 onward. The complex has two camps: Mina, at an altitude of 4,500 meters, and Molino, at 4,000. A 47-kilometer road connects it to the railroad at Tres Cruces, from which about 100,000 tonnes leave each year. It employs about 1,500 people and provides 1,542 homes.
The agreement with the Canadian firm Wright Engineers responds to a problem that the article explains: at greater depth, the ore grade falls and more must be extracted. In the September issue, Jorge Cuomo remembers Enrique M. González in the Puna: he worked in the office that kept the workers’ time and studied at night.
In 1990 the plan is to go from 2,000 to 3,000 tonnes per day. In 1993, with the fall in prices and the appearance of manganese, the company cuts production by 30% and reduces its workforce from 1,800 to 595 people. In November 2020 the mine enters care and maintenance.