LSC Lithium: Positive PEA results of 20,000tpa lithium carbonate operation from Pozuelos-Pastos Grandes project

3 mins lectura
LSC Lithium: Positive PEA results of 20,000tpa lithium carbonate operation from Pozuelos-Pastos Grandes project
LSC Lithium: Positive PEA results of 20,000tpa lithium carbonate operation from Pozuelos-Pastos Grandes project
Compartir:

LSC Lithium Corporation announced that it has completed the Preliminary Economic Assessment (“PEA”) for its Pozuelos-Pastos Grandes (“PPG”) Project, located in Salta province.

Highlights include:

  • US$762 million after-tax NPV at 8% discount rate and IRR of 30%
  • CAPEX estimate of US$338 million with 34% of estimate at PFS level accuracy
  • OPEX of US$2,994/t of lithium carbonate over life of mine
  • Mine life of at least 20 years with initial production in 2021 and steady state in 2024
  • Designed for production of 20,000tpa of battery grade lithium carbonate
  • Combined PPG Project Resource of 2,617,000 tonnes LCE in Measured and Indicated category and 938,500 tonnes LCE in the Inferred category
  • Process development supported by benchscale test work. Pozuelos brine chemistry, in particular is amenable to excellent process performance

LSC’s President and CEO, Ian Stalker, noted, “These results support our view that PPG is one of the most advanced and economically viable lithium projects in Argentina. Operating costs are in the lowest quartile globally, the capital requirements are manageable, and we are excited by the large resource, which leaves room for future upsizing.”

“This important development milestone will be further supported by the Environmental Impact Statement which we intend to submit to the Salta mining secretary. We look forward to 2019, when further pilot testing and geotechnical work at the project will support further data for a full Feasibility Study.”

 

Unique Project Advantages

The PPG Project enjoys certain unique advantages, which support a rapid development schedule, and low capital and operating costs:

  • LSC controls over 90% of the area of the Pozuelos salar and its surroundings. This advantageous position makes siting of infrastructure, extraction of fresh water and preparation of brine-extraction models extremely simple. In this way, sustainable pumping of brine can be ensured.
  • Geotechnical conditions in the mature portion of the Pozuelos salar are such that construction of evaporation ponds can occur on the salar surface at low cost.
  • For the two reasons above, it was decided to locate all infrastructure at Pozuelos, with only extraction wells and a pipeline located at Pastos Grandes.
  • Pozuelos’ proximity to the existing Fenix gas pipeline ensures that only a 26km connection needs to be constructed. LSC has been allocated gas capacity on this pipeline by the gas supply company.
  • At least three separate sources of fresh water have been identified and road access is readily available.
  • The brine chemistry of the Pozuelos and Pastos Grandes salars complement each other. Test work has shown that an efficient evaporation path can be pursued to produce a high grade and high purity concentrate for feeding into the lithium plant ensuring high recovery rates.
  • LSC developed a processing method that is based on conventional and proven operations for lithium brines.

GHD was selected in June 2018 as the preferred engineering company for the execution of the PEA after an extensive selection process, where LSC solicited expressions of interests and proposals from 14 different companies across the globe. GHD offers extensive experience in the design and implementation of lithium projects with brine feedstock. GHD has experience in Argentina’s Puna plateau, working with Orocobre as the preferred engineering service provider for the expansion project at Sales de Jujuy operation, as well as providing services for Neo Lithium’s Tres Quebradas project. GHD also supports major lithium producers in Chile and Australia along with other lithium developers in the South American region.

Publicado por: Panorama Minero

Categoría: Noticias

¿Querés recibir noticias del sector y de las iniciativas de Panorama Minero?


Suscribite a nuestro boletín.

Imagen ilustrativa para el artículo: MARA recibe reconocimiento por su plan de restauración ambiental

MARA recibe reconocimiento por su plan de restauración ambiental

El Proyecto MARA, ubicado en la provincia de Catamarca, fue distinguido en el concurso sobre gestión de biodiversidad organizado por la Cámara Argentina de Empresarios Mineros (CAEM) y la Fundación ProYungas. La iniciativa premió su programa de revegetación, desarrollado como parte del plan de cierre de la mina Alumbrera.

Proveedores: Sandvik incorpora control remoto multipunto en perforación de superficie

Proveedores: Sandvik incorpora control remoto multipunto en perforación de superficie

Sandvik Mining anunció una nueva funcionalidad en su sistema AutoMine®: Surface Fleet, una herramienta que permite operar y supervisar más de 15 equipos de perforación i-series desde cualquier ubicación conectada. La solución apunta a mejorar la continuidad operativa durante cambios de turno, reducir tiempos de inactividad y facilitar la administración remota de flotas en operaciones de superficie.

Proyecto Altar culmina su temporada con una exitosa campaña

Proyecto Altar culmina su temporada con una exitosa campaña

Aldebaran Resources finalizó la temporada con más de 25 mil metros perforados y presentará en septiembre su Estudio Económico Preliminar (PEA), que ofrecerá una primera visión integral sobre la viabilidad económica del proyecto.

Transporte más sustentable en el norte del país

Transporte más sustentable en el norte del país

La empresa tucumana de logística refrigerada Fríos del Norte SRL adquirió 53 camiones Super R500 tras comprobar en operaciones reales una mejora del 10% en el consumo de combustible.