LSC Lithium Corporation announced encouraging progress on exploration and pump testing for its Pozuelos-Pastos Project (“PPG”). The Company has engaged the internationally recognized engineering consultancy company GHD Limited to undertake a preliminary economic assessment (“PEA”) on this combined PPG Project due to be completed by end of Q4 2018.

 

Pozuelos Highlights:

  • Three of the six planned pump tests have been completed with grades of up to 731mg/l from well SP-2017-10W1.
  • 14.394 line km of seismic data acquired along one survey line.
  • Construction of access roads and drilling platforms underway for exploration drilling in the north east of the salar.
  • Start of deep exploration drill hole PZ-18-01 in the centre of the salar, currently 315.03m.
  • Construction of the Pozuelos exploration camp to be completed in August 2018. Camp will be converted to administration offices during operations.
  • Updated Mineral Resource expected in Q4 2018.

 

Pastos Grandes Highlights:

  • Significant progress achieved with drill hole PG-18-01 currently 541.4m. Average downhole grade of 491mg/l from surface to 474.62m depth.
  • 15.372 line km of seismic data acquired along six survey lines.
  • Maiden Mineral Resource Estimate expected end of Q3 2018.

 

PPG Project Highlights:

  • Environmental Baseline Studies completed at both salars.
  • Ongoing PEA work for completion in Q4 2018.

 

LSC’s President and CEO Ian Stalker, noted, “The PPG Project is now in full data acquisition phase to support the PEA and the subsequent Prefeasibility Study. Furthermore, the significant progress on the environmental baseline studies will ensure that we can submit our Environmental Impact Statement to the Regulator before year end. We remain on-track for a resource announcement at Pastos Grandes at end of Q3 2018. It is also important to note the added future operational flexibility (blending, pumping options, etc.) and increased scalability of production volumes this combined salar approach gives us at Pastos Grandes and Pozuelos, as well as being much more environmentally appropriate in having one, instead of two, footprints for an operational plant.”

Publicado por: Panorama Minero

Categoría: Noticias

¿Querés recibir noticias del sector y de las iniciativas de Panorama Minero?


Suscribite a nuestro boletín.

Imagen ilustrativa para la noticia: Catamarca proyecta un laboratorio minero estratégico  | Panorama Minero

Esta iniciativa avanza en articulación con la Universidad Nacional de Catamarca (UNCA), en el marco del proceso de traspaso y nueva conformación de Yacimientos Mineros de Agua de Dionisio (YMAD), instancia que otorgará a la provincia control mayoritario en la conducción de la empresa minera estatal junto a la Universidad Nacional de Tucumán (UNT).

Imagen ilustrativa para la noticia: Del aval político a la ingeniería: PSJ define su acceso energético | Panorama Minero

Firmó un acuerdo con Distrocuyo para iniciar los estudios que permitan la construcción de una nueva línea de 220 kV y una estación transformadora en la alta montaña mendocina. De esta manera buscan ordenar la ingeniería del proyecto y reducir la incertidumbre en una operación de alta demanda energética.

Imagen ilustrativa para la noticia: Catamarca asume el control mayoritario de YMAD  | Panorama Minero

El Gobierno de la provincia de Catamarca y la Universidad Nacional de Tucumán (UNT) concretaron la firma de convenios estratégicos que completan el proceso de transferencia de Yacimientos Mineros de Agua de Dionisio (YMAD).