Galan Lithium published its Quarterly Activities Report for the quarter ended 31 December 2025. Phase 1 construction at Hombre Muerto West (HMW), well timed to take advantage of a lithium market recovery
By Panorama Minero
During the quarter, Galan continued to focus on the construction of Phase 1 at its 100% owned HMW lithium brine project located in Catamarca province. Galan delivered a series of material advancements at HMW that firmly position it to transition from developer to producer in H1 2026.
Speaking on the progress achieved this quarter, Managing Director Juan Pablo Vargas de la Vega said: “This was a strong quarter for Galan, marked by meaningful progress in construction activities at Hombre Muerto West. With construction funding for Phase 1 secured and workstreams well advanced, we remain firmly on track for first production in H1 2026. Importantly, we continue to assess the opportunity to expand Phase 1 capacity from 4,000 tpa LCE to a capacity above 5,000 tpa LCE by leveraging existing infrastructure and improving project scale. 2026 will be a transformative year for Galan and its shareholders, as we move toward production and cash flow at a time of vastly improved sentiment and market conditions for the lithium sector.”

Project Execution – Hombre Muerto West
Execution of Phase 1 at HMW advanced materially during the quarter, with construction progressing in line with schedule toward first production in H1 2026.
The Phase 1 nano-filtration plant was assembled and tested in Sydney, confirming performance in accordance with design parameters. Following testing, the plant was containerised and dispatched for shipment to site, with delivery expected in early 2026 and commissioning to follow.
On site, substantial progress was made across evaporation ponds and plant infrastructure. Ponds 4 and 5 were redesigned and constructed to support the 4,000 tpa LCE Phase 1 production rate. Earthworks for the process plant were completed and the concrete foundation slab poured. Engineering and procurement activities remained focused on integrating the nano-filtration facility with the pond system. The majority of long-lead items are now on site or in transit.
The Company maintained a strong safety and environmental record during the quarter, with no lost time injuries and continued compliance with regulatory approvals and community engagement commitments. Overall, Phase 1 execution at HMW continues to progress as planned, supported by strong coordination between Galan, its contractors and strategic partners.



























