Los Azules Advances Infrastructure Works in Calingasta

2 minutes
Los Azules Advances Infrastructure Works in Calingasta
Los Azules reorganises its logistics activities to maintain the work schedule.
Share:

The Los Azules copper project, located in San Juan, announced a reorganisation of its logistics activities for the coming weeks. This will involve relocating personnel from the Candadito camp to Calingasta and continuing infrastructure works along the lower sections of the project's access road.

By Panorama Minero

The decision reflects the need to concentrate work on sections where ground conditions change with the arrival of the snowmelt period, with the aim of maintaining the work schedule and advancing preparations for the infrastructure required for the future construction stage.

Access Road Works

Over the coming weeks, activities will focus on work on the culvert at kilometre 0, on the Calingasta River, and reinforcement of critical sections of the access road between Barrialito and that location.

In parallel, engineering work on the bypass bridge will continue, with the aim of beginning the prefabrication of its main beams within the local community.

According to the company, this approach also includes the creation of employment opportunities for local residents.

Water management works at the Calingasta site will also be reinforced as part of the planned improvements to support project activities.

Reorganisation of Activities at Candadito

As part of this plan, the 36 workers currently based at the Candadito camp will be relocated to Calingasta, where they will continue carrying out their duties over the coming weeks.

Candadito is located at an altitude of 3,150 metres above sea level, 54 kilometres from Villa Calingasta and 79 kilometres from Barreal. The facilities provide logistics support and serve as a personnel and equipment changeover point for those involved in project activities.

Los Azules stated that the camp remains in good condition, has adequate supplies of water, food and fuel, and that its access road remains operational.

Personnel transfers will be carried out according to a planned schedule, during daylight hours and using light vehicles. Journeys will be coordinated by the Roads Supervision team and the Safety team, which will maintain communication throughout the transfers.

The reorganisation will enable human and operational resources to be concentrated on the planned works at lower elevations, while preparations for the access infrastructure to Los Azules continue.

Through these measures, the company expects to maintain its activity programme and advance the works required for the future construction of the copper project in Calingasta.

Published by: Panorama Minero