Puna Operations surpasses productive goals of 2018 – Plans for 2019

2 mins min lectura
Compartir:

SSR Mining Inc. reported fourth quarter and year-end 2018 operating results. Related to Puna Operations (a 75%/25% with Golden Arrow, located in Jujuy province), it exceeded the upper end of the revised annual silver production guidance with a total of 3.7 million ounces. With the declaration of commercial production at the Chinchillas mine in December 2018, SSR Mining produced 1.2 million ounces of silver in the fourth quarter, a 79% increase over the third quarter, as the mill averaged nearly 3,800 tonnes per day.

In 2018, Puna Operations produced a total of 3.7 Moz of silver, 8.8 million pounds of zinc and 3.1 million pounds of lead. The quantity of silver ounces sold for 2018 totaled 3.8 Moz. On an attributable basis of 75%, silver production and sales in 2018 totaled 2.8 Moz and 2.8 Moz, respectively. During the year, the ore was ground at an average of 3,890 tons per day. The ground ore contained an average silver grade of 114 g/t. The average metallurgical recovery of silver was 72.1%, an increase of 3% compared to 2017.

In the fourth quarter of 2018, silver production was 1.2 Moz, an increase of 79% in relation to the third quarter, mainly due to the increase in the tonnage of ground ore of higher grade of Chinchillas.

During the fourth quarter, the ore was ground at an average of 3,720 tons per day. In December, the ore was obtained exclusively from Chinchillas and reached a milling rate of 3,605 tons per day. The ore processed in the fourth quarter contained an average silver grade of 133 g/t, an increase of 38% compared to the third quarter of 2018, due to the processing of high quality ore from Chinchillas in December. The average silver recovery in the fourth quarter was 81.5%.

In Puna Operations, with the commercial start of Chinchillas in the open sky already reached, the year 2019 marks the first full period of mineral production at the Chinchillas mine, transported for processing at the Pirquitas mine plant. Puna Operations is expected to produce between 6 Moz and 7 Moz of silver. Capital investments in Puna Operations of US$12 million include US$5 million for the maintenance of the mine equipment and US$ 5million for the maintenance of the plant equipment.

Publicado por: Panorama Minero

Categoría: Noticias

¿Querés recibir noticias del sector y de las iniciativas de Panorama Minero?


Suscribite a nuestro boletín.

Imagen ilustrativa para la noticia: Iglesia: cuando la minería sembró emprendedores con mirada de futuro | Panorama Minero

Tres emprendedores nacidos en el departamento del norte de San Juan relatan cómo la llegada de la minería metalífera y la puesta en marcha de Veladero les permitió transformar pequeños proyectos familiares en proveedores formales, adquirir conocimiento técnico y construir emprendimientos con visión de largo plazo, pensados para sostenerse más allá de la vida útil de la mina.

Imagen ilustrativa para la noticia: Patagonia Lithium: Actualización de Perforación en Formentera | Panorama Minero

La compañía anunció que ha comenzado la perforación del Pozo 6 hasta una profundidad de 131 metros. Se han recuperado unidades litológicas de arena y limo con observaciones de alta porosidad. Formentera se encuentra en la provincia de Jujuy.

Imagen ilustrativa para la noticia: Ricardo Alonso: “Tenemos minería desde hace más de 500 años y vamos a tener minería por otros 500 años.” | Panorama Minero

Ricardo Alonso es una de las voces más autorizadas en materia minera y académica de Salta. Geólogo, escritor, es Profesor Emérito de la Universidad Nacional de Salta, miembro de la Academia Nacional de Ciencias. Además, fue Secretario de Minería de Salta en dos periodos y Presidente de la Comisión de Minería de la Cámara de Diputados. Alonso comparte una perspectiva histórica de las carreras mineras en Salta, la dinámica con la demanda de la industria y los desafíos actuales.